Author : Zhao, X; Lee, T. S.
Category : Journal Article
Department : Supply Chain and Information Management
Year / Month : 1996
ISSN: 0953-7287 (Print), 1366-5871 (Online)
Source : Production Planning and Control, Vol.7, No.2, pp.144-161.

Abstract

    This paper extends the studies by Sridharan, Berry, and Udayabhanu from single-level MPS systems to multilevel material requirements planning (MRP) systems, and examines the impact of product structure, lot-sizing rules and cost parameters upon the selection of MPS freezing parameters under deterministic demand. A model is built to simulate the master production scheduling and material requirements planning operations in a make-to-order environment. The results show that all the MPS freezing parameters studied have a significant impact upon total inventory costs and schedule instability in multilevel MRP systems. First, the order-based freezing method is preferable to the period-based method. Secondly, the study finds that increasing the freezing proportion reduces both total inventory costs and schedule instability. This finding contradicts the finding by Sridharan et al. in single-level systems. Thirdly, the study finds that a higher replanning periodicity results in both lower total inventory cost and lower schedule instability. The study also indicates that the product structure and lot-sizing rules do not significantly influence the selection of MPS freezing parameters in a practical sense under most situations. However, the cost parameter seems to significantly influence the selection of replanning periodicity.